    • CommentAuthordarkpollo
    • CommentTimeJun 20th 2008
     permalink
    Is there any way to update a lot of tasks at the same time.
    I want to change the date or something to 20 diferent tasks.
    is there anyway to change them all at once?
    • CommentAuthoradmin
    • CommentTimeJun 21st 2008
     permalink
    By assigning them to the same milestone, and then changing the milestone date. :-)

    You could also have a look at the gantt view, as that lets you change the dates / estimates of tasks easily.

    -- Erlend
    • CommentAuthordarkpollo
    • CommentTimeJun 23rd 2008
     permalink
    Posted By: adminBy assigning them to the same milestone, and then changing the milestone date. :-)

    You could also have a look at the gantt view, as that lets you change the dates / estimates of tasks easily.

    -- Erlend


    good answer, but i have another question...
    How to assign 20 task to a new milestone at once? ;)
    Gantt view is good for this, but it doesnt archive the changes, so i do not want to use a lot.
    • CommentAuthoradmin
    • CommentTimeJun 23rd 2008 edited
     permalink
    Browse -> Group By Milestone -> Organize Tasks -> Drag n' drop the tasks you want into the milestone.

    -- Erlend
    • CommentAuthordarkpollo
    • CommentTimeJun 24th 2008 edited
     permalink
    wow :)
    Great!
    Thank you Erlend.